Sprint 1

Sprint report for DHSC PIM Sprint 1

Banana

What we did last week

  • Agree ways of working
  • Defining goals and KPIs
  • Drafting user stories
  • Exploring what we want to take into user testing
  • Mapping the as-is service
  • Mapping users and stakeholders
  • Planning initial 2 user group workshops (data consumer)
  • Completed first backlog refinement session
  • Review participant list and address gaps for alpha
  • Setting up service standard deck
  • Conducted two data consumer workshops

What we’re planning to do this week

  • Content: Explore how the service could be maintained and improved in the future
  • Design prototypes for workshops
  • Diagram possible data flows for collaborative maintenance
  • Document attempts to match MHRA data directly with GUDID
  • Document the MHRA data schema
  • How might we… content statements
  • Identify possible PIM prototyping options
  • Investigate sign-in options (within MHRA/DHSC)
  • MHRA/DHSC Tech appraisal
  • Planning initial 2 user group workshops (data providers)
  • Start diagrams for technical architecture

Goals

We have one goal for this sprint (two-week period)

  • Find out how people feel in NHS trusts about proposed view of 13 fields In progress

Things to bear in mind

  • We did a mini “Show and tell” showcasing our work last week on Wednesday 1st May
  • Our next show and tell will be on Tuesday 14th May

These are are currently identified risks and issues

  • [Issue] Engagement with manufacturers in a maintenance process
  • [Risk] Final ownership
  • [Issue] Different people building different overlapping systems
  • [Issue] NHS trust infrastructure to be able to consume data from PIM
  • [Risk] Getting service assessment booked
  • [Risk] User availability