Sprint 37 - Lemur
Monday, July 28, 2025 in Project Reports
Sprint 37 - Lemur Things to bear in mind There was no weekly report last week What we did last week feature: Improve logic for revised updates to data values feature: Include type of update selected as heading in data table task in update journey …
Sprint 36 - kangaroo
Monday, July 14, 2025 in Project Reports
Sprint 36 - kangaroo What we did last week task: Confirm whether variable values that didn’t exist in the past should have data values with ’not applicable’ added when they are used in for later statistics task: Add HTTP …
Sprint 35 Mid - Jackalope
Monday, July 07, 2025 in Project Reports
Sprint 35 Mid - Jackalope What we did last week feature: Filter selection counter (JS only) feature: Batch select / deselect filters feature: Filter iterations after initial consumer testing feature: Adding missing data value shorthand to the system …
Sprint 35 - Jackalope
Monday, June 30, 2025 in Project Reports
Sprint 35 - Jackalope What we did last week feature:Sticky first row task: Run unmoderated accessibility testing with consumers task: Analyse round 5 of consumer user testing task: Load testing of dev environment -fixes and performance improvements …
Sprint 34-mid - Ibex
Monday, June 23, 2025 in Project Reports
Sprint 34-mid - Ibex What we did last week feature: Consumer navigation to API documentation feature: Mandate notes column in dataset creation and validate this feature: Translate to Welsh for consumer testing feature: Implement history tab on …
Sprint 34 - Ibex
Monday, June 16, 2025 in Project Reports
Sprint 34 - Ibex What we did last week feature: Write cookies statement task: Run end-to-end UI consumer testing without sorting or filtered downloads task: Plan unmoderated accessibility testing with WG staff networks task: Prepare Marvell …
Sprint 33-mid - Horse
Tuesday, June 10, 2025 in Project Reports
Sprint 33-mid - Horse What we did last week task: Onboard publishers cohort 4 task: Plan data table only consumer testing task: Design table sort (cancelling a selected sort) task: Document patterns and components task: [Spike] Agree strategy for …
Sprint 33 - Horse
Monday, June 02, 2025 in Project Reports
Sprint 33 - Horse What we did last week task: Explore requirements for date reference data not fully known task: Plan data table only consumer testing task: Map the landscape of data services in Wales task: Explore how we might automate the pivoted …
Sprint 32-mid - Gecko
Tuesday, May 27, 2025 in Project Reports
Sprint 32-mid - Gecko What we did last week feature: Flatten a Cube feature: Investigate how much data we actually have. task: Start onboarded publishers cohort 3 first task task: Update create / update user flow map task: Reference data policy …
Sprint 32 - Gecko
Monday, May 19, 2025 in Project Reports
Sprint 32 - Gecko What we did last week feature: On dataset overview, “Continue…” link should be first on list feature: Remove all categories apart from geography from reference data in SW3 task: Iterate solution design document to …