Posts in 2024
  • Sprint 5 - Fabulous F-Value

    Monday, April 22, 2024 in Project Reports

    What we did last week Create metadata database and link to assets in datalake (Goal) Implementation of Internationalisation Create summary document of 1st round testing Advertise user consumer survey more widely What we’re planning to do this …

    Read more

  • Sprint 4 - Educated Estimation (mid-sprint)

    Monday, April 15, 2024 in Project Reports

    What we did last week Prepare new data consumer participant list Organise 5 SW participants for next round of testing SPIKE: Presenting data ingestion, data format options for next round of testing What we’re planning to do this week Access …

    Read more

  • Sprint 4 - Educated Estimate

    Tuesday, April 09, 2024 in Project Reports

    What we did last week Spike - explore Reference data and linking - data modelling and standardisation: What we’re planning to do this week Create metadata database and link to assets in datalake Reference data - controlled vocabularies such as …

    Read more

  • Sprint 3 - Descriptive Statistics (mid-sprint)

    Tuesday, April 02, 2024 in Project Reports

    What we did last week Recruit participants for testing the alpha prototype Data consumer - research analysis Conduct remote usability testing of our prototypes - data consumers Data processor/publisher - Prototype (iteration 1) Data consumer - …

    Read more

  • Sprint 3 - Descriptive Statistics

    Monday, March 25, 2024 in Project Reports

    What we did last week Disseminate the survey to the data publishers Define concepts for prototype testing Recruit participants for testing the alpha prototype Session to look at current product analytics Upload data to a data lake (includes Demo) …

    Read more

  • Sprint 2 - Curious Correlation (mid Sprint)

    Monday, March 18, 2024 in Project Reports

    What we did last week Disseminate the survey to the data publishers. Implement the data consumer bilingual survey using Smart Survey Plan session to look at current product analytics Terms of References Define concepts for prototype testing What …

    Read more

  • Sprint 2 - Curious Correlation

    Monday, March 11, 2024 in Project Reports

    What we did last week Create a plan for prototype testing Pilot data processor feedback survey with two participants IaC a data lake Points / Milestones against which project will be tracked / paid Mapping data on the current service Examination of …

    Read more

  • Sprint 1 - Buoyant Boolean (mid Sprint)

    Monday, March 04, 2024 in Project Reports

    What we did last week Conduct an analysis of potential platforms (e.g., within MS Azure) Is this service applicable for a service assessment? Initial / High level stakeholder map Set up a separate Azure environment for Marvell. Conduct a data …

    Read more

  • Sprint 1 - Buoyant Boolean

    Monday, February 26, 2024 in Project Reports

    What we did last week Conduct an analysis of potential platforms (e.g., within MS Azure) Is this service applicable for a service assessment? Initial / High level stakeholder map Set up a separate Azure environment for Marvell. Conduct a data …

    Read more

  • Sprint 0 - Arbitrary Asymptote

    Monday, February 19, 2024 in Project Reports

    What we did last week Initial architecture discussion Ways of working meeting Project board set up What we’re planning to do this week Conduct a data architecture review Set up a separate Azure environment for Marvell Initial / High level …

    Read more