Sprint report for the StatsWales3 Sprint 13 (mid-sprint)
Weekly report
The Letter n

What we did last week
- Update Solution design document
- Plan for project board
- [TASK] Investigate missing values in SW2
What we’re planning to do this week
- OData loader
- Conduct and analyse tree test of topics taxonomy (with publishers)
- KAS Analysis of data migration exercise (questionnaire)
- Prototype update journey
- Discussion - what needs to happen next to progress data migration?
- Planning next round of research with publishers.
- Stand up the service in WG Azure
- Happy path user flow for updating a dataset
- [SPIKE] Data access strategy
- Implement domain model on back-end
- Data domain model
Sprint goals
These are the goals that we set for this sprint:
Complete “publish a dataset” up to metadata (development) In progress
Azure pipeline in WG estate (dev ops) In progress
Get full download of most recent OData (data) In progress
Things to bear in mind / What’s blocking us
The following things are still blocking the progress of the project
- Access to the source data We have received another data file today, which we are hoping will contain everything that we need
- Azure subscriptions We have requested further permissions which are required to build the pipeline from the Marvell estate to the WG estate
Screen shot of risks and issues board

Risk impact chart