What we did last week
- Start to understand the needs being met by the current OData service
- Connect prototype designs with stories
- Use SW2 data to build prototype data for testing new system
- Respond to Jack (CDPS) regarding data standards
- Plan engagement for Welsh Statistical Liaison Committee event (5th June)
- Welsh statistical liaison committee meeting (WSLC)
- Plan for project board - Monday 10th
- Adjust the build pipeline
What we’re planning to do this week
- Implement ‘Choose a dataset to upload
- Understand the variety of data sources
- Finalise Solution Design Document
- Implement ‘Create a new dataset’ page
- Align roadmap and release plan
- Understand and reconcile geographical coverage options
- Implement auth into relevant services
- Model a mock data cube - Architecture
- High-level plan for user research in Beta
- [SPIKE] Gel React components
- Implement ‘Name the dataset’
- Analyse Stats Wales 2 data
- Register Dynamics - Cyber Essentials Plus
- Testing prototype round 3 - with publishers
- Data audit for data migration
- Data domain model
- Analyse findings from ‘Browse by topic’ exercise with data consumers
Goals
These are the goals that we set for this sprint:
Complete testing of prototype round 3 with publishers In progress
Implement Auth on the beta application In progress
Things to bear in mind / What’s blocking us
The following things are still blocking the progress of the project
- Access to the source data
We are exploring another approach to getting a copy of the data for which we hope to get approval
- Agreement on access for Marvell subcontractors
We are reviewing with our subcontractors the oustanding points that resulted from the Cyber Essentials Plus audit - Architecture form - Azure subscriptions
We have a meeting with the architect’s office to review the current Service Description Document